answersLogoWhite

0


Best Answer

As per the Project Management Terminology, the longest path in a project sequence of activities is called the Critical Path. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date.

Since this path is going to determine the schedule/delivery date of the project, it is called the critical path.

User Avatar

Wiki User

13y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: Why is critical path the longest path?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

Is the critical path always the longest path?

The critical path is the sequence of activities that takes all dependencies into account. Thus, it determines the duration of the project, and is necessarily the longest path.


Critical path of a project?

The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date


What is defined by a critical path?

The Critical Path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date. Critical Path is one of the key outputs of the Project Schedule Creation activity


What is critical path?

In Project Management the Critical Path is the series of tasks that must finish on time for the entire project to finish on schedule. Each task on the critical path is a time critical task. You can also think of it as:the longest path from start to finishor the path without any slack,the path corresponding to the shortest time in which the project can be completed.


How do you explain the critical path analysis?

Critical path method - This is the schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram. The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date.


Can there be more than one critical path in a given project schedule?

Yes. Practically that is perfectly possible. A Critical Path is the longest path between the start and end points and it is possible that there are multiple critical paths. Critical Paths are extremely important while creating a project schedule


What are the uses of the critical path?

These critical path enables PMs to know which activities (tasks) are essential for Project Completion (can delay the project), and which activities are not. It also gives a clear idea on how to accelerate the projects (eg by adding more resources to the tasks on the critical path).Answer:Critical Path Method: This is the schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram. The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date


Why critical path is critical to project management?

Critical path method - This is the schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram. The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start dateThe Critical Path and Duration of the Critical Path, gives the project manager a clear picture of how long all the activities can take to complete. It also helps him to identify the flexibility in the project schedule by calculating the early and late start and finish dates of each activity on each path. The schedule flexibility of an activity is measured by the positive difference between the late start date and the early start date for the activity and is called float time or total float.


What is the significance of Critical Path Analysis in Project development?

Critical path method - This is the schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram. The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start date.The second important feature of the critical path method is to identify the flexibility in the project schedule by calculating the early and late start and finish dates of each activity on each path. The schedule flexibility of an activity is measured by the positive difference between the late start date and the early start date for the activity and is called float time or total float.Without a proper Critical Path Analysis, an efficient Schedule for the Project cannot be created


Give detail of critical path analysis network?

See the link section for a detailed explanation. In a nutshell, the idea is to calculate those tasks that take the longest and cannot be skipped nor done in parallel. These tasks become your critical path - which define the shortest amount of time the project will take to complete. Some projects may have more than one critical path; though the one with the longest time frame will define the time frame. All other tasks can be done in parallel or can be skipped. Once the critical path is defined, then one can try to redefine certain components so as to remove them from the critical path. The fewer items on the critical path the smaller the risk of failure and the easier it is to get more things done in parallel.


What is critical chain method?

Critical path method - This is the schedule network analysis technique used to identify the schedule flexibility and the critical path of the project schedule network diagram. The critical path is the longest path (sequence of activities) in a project schedule network diagram. Because it is the longest path, it determines the duration of the project and hence the finish date of the project given the start dateThe important feature of the critical path method is to identify the flexibility in the project schedule by calculating the early and late start and finish dates of each activity on each path. The schedule flexibility of an activity is measured by the positive difference between the late start date and the early start date for the activity and is called float time or total float.


What is the differences between critical path and slack time?

The critical path is the longest path through a project, indicating the shortest possible time needed to complete the project. Slack time is the amount of time a task can be delayed without delaying the project completion. Tasks on the critical path have zero slack time, while non-critical tasks have slack time.