The strength of concrete on the 28th day is considered full strength with regard to the engineering calculations for its use.

Concrete continues to get hard for 100 years or more, as long as it has water on it now and then.

For a 6-sack concrete mix, its 28 day compressive strength should be at 4,000 psi or greater.

User Avatar

Wiki User

12y ago
This answer is:
User Avatar

Add your answer:

Earn +20 pts
Q: What is ultimate 28 day concrete strength?
Write your answer...
Submit
Still have questions?
magnify glass
imp
Related questions

What class of concrete is stronger ST2 or ST4?

ST 4 concrete is the stronger out of the two. ST4 is equivalent of 16 kn at 28 day strength where as ST2 is only 8 kn at 28 day strength.


What is mean by m20 of grade concrete?

it is concrete mix which gain strength 20kn/mm2 in 28 day of curing....


What is the strength in psi is the M20 Concrete?

how much tensile strength of M20 grade concrete at 28 Days


What is m 30 concrete?

It is the grade of concrete which indicates the strength of concrete after 28 days curing. M #) means the strength of concrete after 28 days of curing will be 30 N/mm2 .


What is the strength of M-30 after 7 days?

Seven days strength of any concrete usually comes 67% of 28 day strength. So 7 day strength of M30 may be .67*30=20.10 MPa


What is strenGth of M-30 after 30 days?

Seven days strength of any concrete usually comes 67% of 28 day strength. So 7 day strength of M30 may be .67*30=20.10 MPa


What is the compressive strength of M15 concrete at 28 days?

15


What is the difference between fc and fcu in concrete?

f ′c: concrete compressive strength at 28 days (compression is negative) fcu: concrete crushing strength (compression is negative)


What is the strength of M40 grade concrete within 28 days?

40N/mm2


What is the Compressive strength of M 50 concrete at seven days?

2/3 times the 28 days strength


Which type of concrete should you use when it must reach its design strength in about 28 days?

concrete made upof ordinary portland cement gain strength in 28days


What is the compressive strength of M10 concrete at 7 days?

For M25 grade concrete the seven days crushing for site condition shall be not less than 67 % of M25, i.e not less than 16.75 N/mm2 But for target strength of M25 for mix design taken i.e for M25 it is 32 and the 7 days strength shall not be less than 22 N/mm2